During the month of October, the laying of the perimeter sheets of the balconies of P1 continues and the bathrooms of P1 and…
Read MoreDuring the month of September in building B, shower trays have been placed on the ground floor and the tiled bathrooms are being…
Read MoreDuring the month of August, in building B, the placement of windows on the ground floor and 3 floors of the first floor…
Read MoreDuring the month of July in the A1 building they are executing the wooden structure assembly works, the acoustic insulation of the floor…
Read MoreDuring the month of June, work is carried out to reinforce the basement floor and to assemble the second floor and the wooden…
Read MoreDuring the month of May, the wooden structure assembly work begins. Pillars concreting works are carried out in the building area. The concrete…
Read MoreDuring the month of April, work is carried out on the assembly of the roof of the basement and the assembly of the…
Read MoreDuring the month of March, execution work is carried out on the floor, foundation work, ironwork and concreting of foundations, pillars and walls…
Read MoreDuring the month of January, work is being carried out on the foundations and pillars of the different work platforms. Work begins on…
Read MoreDuring the month of November, foundation work, pouring, rebar and concreting of foundations, as well as rebar of walls and pillars, are carried…