Construction Process Jeroni Pujades
During the month of August, in building B, the placement of windows on the ground floor and 3 floors of the first floor began, with Euronit plates on the balcony façade and the walkway façade. The placement of galvanized profiles (cladding and partitions) continues up to P3. The polyurethane spray has been applied to all profiles.
In building A1, the structure of galvanized tradossats profiles and partitions on the ground floor has been placed. Polyurethane spray has been applied on the ground floor, P1, P2 and P3, and fire retardant paint has been applied to all the lintels of the A1 building. In building A2, the installation of CLT vertical panels on the ground floor has begun.