Multi-family dwellings

Construction Process Cobo

During the month of October, work began for the installation of the earth network in the foundation slab. The waterproofing works are being…

Read More

Construction Process Major de Sarrià

During the month of October, the drilling and grouting of all the provisional anchors on the first level, pending stressing, have been carried…

Read More

Construction Process Sostres

During the month of October the 5th floor is being formed and the staircase from basement -2 to 2B is being assembled. Work…

Read More

Construction Process Bagaria UE1

During the month of October, work continues on the placement of panels on the façade and the formation of plasterboard partitions, as well…

Read More

Construction Process Jeroni Pujades

During the month of October, the laying of the perimeter sheets of the balconies of P1 continues and the bathrooms of P1 and…

Read More

Construction Process Torre Hospitalet

During the month of October, mechanisms and air conditioning grilles, telecos inside homes and exterior carpentry have been installed. The kitchen and countertop…

Read More

Construction Process Vernet

During the month of October, formwork has been placed to concrete some of the remaining sections of the crowning girders of Antoni Torrella…

Read More

Construction Process Major de Sarrià

During the month of August, the execution of the micropiles in the area of the masonry wall and the guide walls of the…

Read More

Construction Process Sostres

During the month of September the slab of the 5th floor has been formed, the roof pillars 4B have been executed and the…

Read More

Construction Process Talamanca

During the month of September, the interior installations of houses and pavements on the 1st floor and rooftops continue to be carried out….

Read More