Construction Process Jeroni Pujades
During the month of July in the A1 building they are executing the wooden structure assembly works, the acoustic insulation of the floor and the ground floor walls of the A1 building is being placed. In building B the acoustic insulation of the floor and walls and the thermal insulation of the floor are being installed. The pavement screeds are being executed up to P2ª and waterproof sheet is being placed on building B facades and the placement of L profiles has begun.