During the month of October, the laying of the perimeter sheets of the balconies of P1 continues and the bathrooms of P1 and…
Read MoreDuring the month of October, mechanisms and air conditioning grilles, telecos inside homes and exterior carpentry have been installed. The kitchen and countertop…
Read MoreDuring the month of October, formwork has been placed to concrete some of the remaining sections of the crowning girders of Antoni Torrella…
Read MoreDuring the month of October, work began for the installation of the earth network in the foundation slab. The waterproofing works are being…
Read MoreDuring the month of October, the drilling and grouting of all the provisional anchors on the first level, pending stressing, have been carried…
Read MoreDuring the month of October the 5th floor is being formed and the staircase from basement -2 to 2B is being assembled. Work…
Read MoreDuring the month of October, work continues on the placement of panels on the façade and the formation of plasterboard partitions, as well…
Read MoreDuring the month of September, the stakeout work and the formation of first face plasterboard dividers in P8 / P9 continue. The plumbing…
Read MoreIn the month of September, the tile for the pool was placed, the construction of the planters and the placement of sheet metal…
Read MoreDuring the month of September, painting works are being carried out and luminaires are being installed and registers are being installed. Painting works…