Construction Process Cobo
During the month of October, work began for the installation of the earth network in the foundation slab. The waterproofing works are being carried out on vertical joints of screen walls and the formation of gravel corking for subsequent placement of the bentonite blanket. Earthmoving work continues on the foundation slab work platform.