During the month of June the fifth module of sheeting walls is being executed in the dividing elevation. The dividing elevation has been…
Read MoreDuring the month of June plasterboard is being taped in common areas, first layers of paint and stockpiling of kitchen furniture. Plasterboard partitions…
Read MoreDuring the month of June, work is carried out to reinforce the basement floor and to assemble the second floor and the wooden…
Read MoreDuring the month of June they have been working on partitioning of P1 and P2. The stairs from P4 to P5 and partially…
Read MoreDuring the month of June the fifth module of sheeting walls is being executed in the dividing elevation. The dividing elevation has been…
Read MoreDuring the month of June the pillars and walls of the P11 were concreted and the formwork was mounted. The dividing walls of…
Read MoreDuring the month of June, paving works were completed and work continues on the assembly of interior and exterior carpentry on the façade….
Read MoreDuring the month of June, installations are being carried out inside the houses, masonry has been carried out above ground. Railings have been…
Read MoreDuring the month of June, the laying of ceramic flooring on the swimming pool platform began. Doors painting sample is done. In the…
Read MoreDuring the month of May, the formwork is being assembled and the ground floor roofing is being completed. Floor 1 pillars are being…