During the month of September, the roof and staircase cassette from P4 to P5 was being reinforced and the post-tensioned slab tendons were…
Read MoreDuring the month of May, the formwork is being assembled and the ground floor roofing is being completed. Floor 1 pillars are being…
Read MoreDuring the month of March the suppression slab was concreted and the containment in the ramp area has already been angled. The simple…
Read MoreDuring the month of January, the reinforcement of the walls is being carried out and the milling continues. The formwork of the northern…
Read MoreIn December, work on the underground structure continues. Go To Project Details
Read MoreDuring the month of November, the construction of slurry walls continued. Go To Project Details
Read MoreDuring the month of October, the construction of slurry walls continued. Go To Project Details
Read MoreIn September, the set-aside to the working platform was completed, the sludge equipment was put in place and containment work began. Go To…