In October, the masonry, the waterproofing of the low tower roofs and the plumbing installations were completed. The execution of second sides of…
Read MoreDuring the month of September, masonry work has been carried out on P9 high tower and P8 low tower. Facade masonry has begun…
Read MoreDuring the month of August, P12 roof slab was concreted. The assembly of Hotpint fences has begun on floor 7 and the first…
Read MoreDuring the month of July, masonry work was carried out on P3 and P4. The stairs from P7 to P8 and plasterboard in…
Read MoreDuring the month of June they have been working on partitioning of P1 and P2. The stairs from P4 to P5 and partially…
Read MoreDuring the month of May, the stairs from the basement to the 2nd floor have been executed. Work has been done on partitions…
Read MoreDuring the month of March, the sub-pressure slab, the two-sided wall, the basement pillars and the pill formwork system for the basement ceiling…
Read MoreDuring the month of February, pile driving and pile caps have been executed. The collection of sanitation pipes has been carried out for…
Read MoreDuring the month of October, work is being carried out to prepare the guide wall and earthworks.