During the month of September the work was carried out. The guide wall and the screens have been built in zone 1. The…
Read MoreIn the month of September, the tile for the pool was placed, the construction of the planters and the placement of sheet metal…
Read MoreIn the month of September, the excavation and staking of the foundations in the two blocks is advanced. The reinforcement of both the…
Read MoreDuring the month of September, the work continues to form anchors in the slurry wall, excavation of the earth cut, on the day…
Read MoreDuring the month of August, the kitchen furniture was installed on floors 7-8, as well as the electric meter centralization room and the…
Read MoreIn the month of September, the guide wall and the screens in Z1 were executed. The sludge plant has been set up in…
Read MoreDuring the month of September in building B, shower trays have been placed on the ground floor and the tiled bathrooms are being…
Read MoreDuring the month of September, masonry work has been carried out on P9 high tower and P8 low tower. Facade masonry has begun…
Read MoreDuring the month of September the slab of the 5th floor has been formed, the roof pillars 4B have been executed and the…
Read MoreDuring the month of September, the stakeout work and the formation of first face plasterboard dividers in P8 / P9 continue. The plumbing…