Construction Process Torre Hospitalet

This past October, it followed the work on the above-ground structure. Work has begun on the structure of the third floor. Go To…

Read More

Construction Process Jeroni Pujades

This past October, foundation work, pouring, rebar and concreting of foundations, as well as rebar of walls and pillars are being carried out….

Read More

Construction Process Residencia Sant Adrià

During the month of October, work is being carried out to prepare the guide wall and earthworks.

Read More

Construction Process Cambrils

In October, SATE work is being carried out on the interior facade of one of the staircase cores and almost all the prefabricated…

Read More

Construction Process Bagaria

This past October, the execution of structural slabs was completed. Work continues on the installations, the dividing walls of the façade and the…

Read More

Construction Process Talamanca

During the month of September, the excavation of the site has continued, as has the construction of the retaining walls, as well as…

Read More

Construction Process Sabons

In September, the set-aside to the working platform was completed, the sludge equipment was put in place and containment work began. Go To…

Read More

Construction Process Torre Hospitalet

In September, work on the above-ground structure continues. The ground floor slab has been completed and work has begun on the structure of…

Read More

Construction Process Bagaria

In September, the concreting and rebar work continues. Work also continues on the façade partitions, interior ceramic partitions, as well as on the…

Read More

Construction Process Cambrils

During the month of September, work continued on the interior dividing walls, assembly of sub-frames, raising of floors, installations… In addition, work was…

Read More