Construction Process Bagaria UE1
During the month of September, the stakeout work and the formation of first face plasterboard dividers in P8 / P9 continue. The plumbing and electricity installation works are being carried out at floor P3 / P4. They are beginning to place the second face of plasterboard dividers on the first floors. The insulation installation work continues on the facade.