During the month of April, work is carried out on the assembly of the roof of the basement and the assembly of the…
Read MoreDuring the month of April, revision work has been carried out. Curbings, wiring, assembly of exterior carpentry, paving, as well as masonry work,…
Read MoreDuring the month of April, the works to channel the facilities in the urbanization began. The installation of kitchen furniture and exterior doors…
Read MoreIn March, the ventilated façade of the 11th, 12th and 13th floors was completed. The SATE facades of the private terraces on the…
Read MoreDuring the month of March, floor 10 and core this floor 10-9 were concreted. The architectural prefabrication has been installed and the recessed…
Read MoreDuring the month of March, the sub-pressure slab, the two-sided wall, the basement pillars and the pill formwork system for the basement ceiling…
Read MoreDuring the month of March, work continues on the crowning beams and the concrete wall. The earth has been lowered to the level…
Read MoreDuring the month of March, execution work is carried out on the floor, foundation work, ironwork and concreting of foundations, pillars and walls…
Read MoreDuring the month of March, face-to-face work visits with all agents have been temporarily suspended due to the exceptional situation generated by the…
Read MoreDuring the month of March, interior urbanization work has been carried out and work on the stairs of general industrialists, wood paneling work…