Construction Process Residencia Sant Adrià
During the month of June they have been working on partitioning of P1 and P2. The stairs from P4 to P5 and partially the leveling mortar and anti-impact sheet in P1 have been executed. The P6 ceiling slab has been concreted and the P7 ceiling slab formwork system has been made. P4 has been unshored and the P1 and P2 frames and downpipes from P1 to P3 have also been assembled. The façade sample has also been presented.