Construction Process Residencia Sant Adrià
During the month of August, P12 roof slab was concreted. The assembly of Hotpint fences has begun on floor 7 and the first layers of plasterboard on floor 3. The leveling mortar has been executed on P3 and the interior installations of electricity rooms on floor 1 and plumbing on floor 2. It has been finished plaster on ceilings P4. And the hood ducts and sanitation have been installed up to P8.