Construction Process Major de Sarrià
During the month of July, the previous tasks of demolition of existing pavements and foundations were carried out of the old sales pavilion and the removal of the drainage pipes and also of the crowning of the wall to the park and the removal of the remains of the wall on the intrados for the execution of micropiles. The containment of the micropile screen has started without locating cemented remains or boluses that prevent their execution. The execution of micropiles continues and the previous tasks of the guide wall are being carried out, planning to concrete during the day.