Construction Process Cambrils
During the month of May there are pending to install the railing on the access ramp to the promotion and it is necessary to finish the fencing of the access areas from the community area.
In ESC 9-10: It is running 2nd side plasterboard, wiring and execution of pourwaters in windows and mounting of blind guides. In ESC 7-8: The 1st plasterboard faces and installations are running. And in ESC 5-6: Masonry work, placement of plasterboard structure and assembly of prefabricated panels.