Construction Process Bagaria UE1
During the month of August the walls of the elevators and the middle floor were concreted with the beams of the P13. The first dividing faces and cladding of PYL have been executed up to P5 and the façade enclosure area in P9, hallway dividing area in P6 and pavement screeds in P7, 8 and 9. The execution of second faces in P1 has begun and P2 of stair 6 and the execution of gero partitions on the ground floor. Sample floor balcony waterproofing has been applied and the PS-2 plasters are continued.