During the month of September, the interior installations of houses and pavements on the 1st floor and rooftops continue to be carried out….
Read MoreDuring the month of July, the installation of railings on the roof and terraces continues, as well as installations inside the houses and…
Read MoreDuring the month of June, installations are being carried out inside the houses, masonry has been carried out above ground. Railings have been…
Read MoreDuring the month of May, masonry execution is carried out on all floors except attic, execution of coffered ceilings and parapets on the…
Read MoreDuring the month of March, the floor 3 floor was executed, the pillars were concreted and the metal pillars installed. The installation of…
Read MoreLast November, the work on the underground structure was carried out. In addition, the reinforcement of tablet 2, the formwork of tablet 3…
Read MoreIn October, the work of concreting isolated and running footings in the parking area was completed. Work on the retaining walls is also…
Read MoreDuring the month of September, the excavation of the site has continued, as has the construction of the retaining walls, as well as…