During the month of October the 5th floor is being formed and the staircase from basement -2 to 2B is being assembled. Work…
Read MoreDuring the month of September the slab of the 5th floor has been formed, the roof pillars 4B have been executed and the…
Read MoreDuring the month of august, the concrete slab 4A has been concreted and the pillars of the 3B floor have been executed. Go…
Read MoreDuring the month of july the slab 3B and the pillars of the slab from 2B to 3B have been forming, the slab…
Read MoreDuring the month of June the fifth module of sheeting walls is being executed in the dividing elevation. The dividing elevation has been…
Read MoreDuring the month of May, the 2nd level of shoring was completed, the shoring of the dividing wall is being carried out. It…
Read MoreDuring the month of March, work continues on the crowning beams and the concrete wall. The earth has been lowered to the level…
Read MoreDuring the month of January, the execution of the micropiles will continue and the platform will be microscoped. Go To Project Details
Read MoreLast November, the execution of the micropiles began in the area of one of the party walls. In addition, the excavation of the…