Construction Process Torre Hospitalet
During the month of August, the kitchen furniture was installed on floors 7-8, as well as the electric meter centralization room and the elevator. The installation of the electrical panel on floor 1 and the outdoor air conditioning units has begun. Works are being carried out on the 14th floor monolayer jambs and centralization of PB meters. Refrigerated and electrical pipelines have been laid out to outside equipment.