Construction Process Cobo
During the month of august work on the execution of the wall on Juan de Juanes street continues. 37 screen modules have been executed out of a total of 40 and there are 2 in execution and bataches of screen wall have also been executed on the elevation of Calle Herrero. The diversion works for company lines (water, electricity and telecos) that affected a corner have already been completed.