Construction Process Torre Hospitalet
During the month of July, work continues on the installation of the elevator, sanitation connections, monolayer, flooring and kitchen furniture, and interior and exterior carpentry work. The installation of handrails, the AFS battery room, centralization of meters and air conditioning grids are carried out. Kitchen furniture is also stocked up to the 12th floor. On floors 3 and 4, the parquet flooring is being installed.