Construction Process Bagaria
In March, the ventilated façade of the 11th, 12th and 13th floors was completed. The SATE facades of the private terraces on the 5th and 10th floors remain to be completed.
We continue with the two sections of the tower’s façade. We continue with the placement of the supporting profiles of the exterior false ceiling of the two buildings, previously the skids have been closed in the UE3 building.