Construction Process Torre Hospitalet
During the month of June plasterboard is being taped in common areas, first layers of paint and stockpiling of kitchen furniture. Plasterboard partitions and false ceiling have been completed on some floors. Refrigeration pipes for the climate installation, screed pavements, waterproofing and balcony flooring are being executed on some floors. In some plants, interior carpentry installation, handrail assembly work continues. The roof tightness test has been carried out.