Construction Process Vernet
During the month of September, a retaining wall inside the plot was concreted on the section of type 6 screens, and another wall on Antoni Torrella street was assembled. To date, 78 screen walls and 19 screen buttresses have been built, distributed among the three streets of the plot. The forecast is to continue making screen walls, buttresses, sections of the crowning girder and retaining walls, and it is expected to start the work of emptying the land. It is still pending to remove the two existing buttresses, giving one to Antoni Torrella street and the other to Ramon Llull street.